WORK is well under way on repairs of the historic Sankey Viaduct ahead of its 200th anniversary.
The project to improve passenger and freight journeys between Manchester and Liverpool over the world’s first railway viaduct is underway.
Network Rail is investing £3.8m to overhaul the viaduct in Newton-le-Willows which opened in 1830.
Although not as well-known, long or iconic as Ribblehead in North Yorkshire, Sankey is hugely significant as the first major railway viaduct in the world, and birthplace of the modern railway.
Also known as ‘Nine Arches’ viaduct, it was designed by railway pioneer George Stephenson to bridge the 160-metre gap over the Sankey valley and built between 1828-1830.
When it opened it connected Manchester and Liverpool to form the world’s first intercity passenger route with a regular timetable as people would recognise today.
The 193-year-old landmark is now having important maintenance ahead of its 200th anniversary in 2030 to secure its future for decades to come.
Over the next four months a team of 25 engineers and scaffolding specialists will:
- Put up scaffolding towers along the span for painstaking repairs to take place
- Repoint mortar using specialist heritage mixes to match the existing materials
- Carry out extensive brickwork repairs
- Paint historic metalwork in heritage colours
- Install strengthening anchors to secure any cracks
- Remove overgrown weeds and plants
- Clean graffiti from the top of the stonework
- Fit three new pairs of pattress plates – metalwork which secures the structure
The viaduct was given Grade I listed status in 1966, and because of that free-standing scaffolding is being used so as not to interfere with the historic structure.
'We want people to know if its huge significance'
Mark Evans, Network Rail Capital Delivery senior programme manager, said: “It’s a privilege to look after so many significant buildings and structures across the rail network, but Sankey viaduct has got to be one of the unsung heroes of Victorian civil engineering.
“Its huge significance in the creation of the railway as we know it today is perhaps not so well known – but we’re hoping to change that. This restoration will not only make sure it looks good to celebrate its 200th anniversary in 2030, but will also secure passenger and freight trains for the future too.”
Laser scanners and drones have been used to map every inch of the Victorian viaduct as part of the major restoration project.
A LiDAR survey was carried out by contractor Commendium in conjunction with heritage consultancy firm Wardell Armstrong.
Drone flights also took place as part of the survey taking high-definition photographs of the Grade I listed structure.
The data gathered was then used to build up the 3D computer model by Network Rail’s specialist computer aided design (CAD) team.
This detailed digital recreation will help engineers make repairs now and closely monitor areas needing any further attention in the future.
Teams have also worked closely with St Helens and Warrington council planners to ensure all the work complies with heritage guidelines.
The major restoration work is expected to take Network Rail four months to complete.